Orchard Hills Landfill Phase XII North
Landfill Cell Construction & Capping
Project Details
Developer:
Advanced Disposal (Waste Management)
Engineer:
Andrews Engineering
Location:
Davis Junction, IL
Work Scope
10 acres of total landfill cell construction
4,000 linear feet of silt fence installation
50,000 cubic yards of excavation to stockpile
60,000 cubic yards of compacted clay liner
40,000 cubic yards of clay borrow excavation
10,000 cubic yards for access pad and containment berm
16,000 cubic yards of drainage layer placement
1,500 linear feet 8” HDPE leachate pipe installation
Gas header pipe installation and valve vaults
All storm structures and pond discharge structures