Charles City Phase VI Cell 1 and Capping
Landfill Cell Construction & Capping
Project Details
Developer:
Waste Management
Engineer:
HDR Engineering
Location:
Charles City, VA
Work Scope
Cell 1
8 acres of clearing and grubbing
9 acres of seeding and mulching
5,500 cubic yards of topsoil stripping
80,000 cubic yards of structural fill
22,000 cubic yards of leachate drainage layer installation
1,200 linear feet of 8” HDPE collection piping
1,900 linear feet of 6” HDPE collection piping
3,500 linear feet of depressurization lines 6” HDPE piping with stone and geotextile wraps
1,100 linear feet 4” odor control pipe
300 linear feet dual-contained forcemain 8” x 12” HDPE piping
1,800 tons perimeter road grading and stone
10,000 square yards erosion control matting
1,500 linear feet of super silt fence
Capping
15,000 cubic yards waste excavation and relocation
24,500 cubic yards 12” intermediate cover
11,000 erosion control matting
1,400 linear feet of down drain trenches and v-ditches
2,600 linear feet of diversion berms
40,000 cubic yards protective cover
12,000 square yards vegetative support layer
15 acres seeding and mulching
5,000 linear feet HDPE pipe of multiple sizes
5,200 linear feet of air and condensate pipe of multiple sizes
6,200 linear feet of 18” Advanedge system