Project Details

Developer:

Hunzinger Construction Company

Engineer:

Pinnacle Engineering Group

Location:

Kenosha, WI

Work Scope

100 acre site warehousing distribution facility for two warehouse buildings

1,100,000 square foot building and a 650,000 square foot building 

175,000 cubic yards of topsoil stripping

400,000 cubic yards of clay excavation to structural fill

Lime stabilization 

40,000 cubic yards of building and parking topsoil respread

Associated pond and parking grading

Stone the building pad and parking

Fine grading and backfill of curbs