Joliet Bulk Barge & Rail
North Laraway Terminal
Intermodal Site Development
Project Details
Developer:
Ragnar Benson Construction
Engineer:
HR Green and Engineered Rail Solutions, LLC
Location:
Joliet, IL
Work Scope
25,000 linear feet of silt fence
200,000 cubic yards of topsoil stripping
1,400,000 cubic yards of clay excavation to fills
1,000,000 square yards of finishing rail/parking areas
5,400 linear feet of diversion berms
7,000 linear feet of backfill curbs
Subballast placement
Drainage pipe